Worldwide standardization of safety-relevant lab and operating equipment (pharma fridges, HEPA filters and more).
Period
March 2023 – June 2025 (28 months)
Effort
440 person-days
Delivery
~90% remote, ~10% on-site at international locations
Global pharma group. Required transparency across in-flight investment and standardization initiatives for safety-relevant lab and operating infrastructure.
Build a clearly structured program and project management to globally standardize technical equipment and the associated business and IT processes — anchored on regulatory, economic and operational criteria. Surface savings potential and provide a sound basis for decisions on equipment use and global technical standards.
Waterfall with classic project plan, work packages, timeline and recurring governance. Structured risk analyses; agile delivery in iterative cycles for implementation work.
Engagement signed off. Program and project steering established, standardization roadmap delivered.